NtM no.21 of 2018  

INFORMATION

River Crouch – Repair of Sea Defences

Mariners are advised that Jackson Hyder will be carrying out embankment repair works on behalf of the Environment Agency at Creeksea and Malyons along a 1.43 km section of the River Crouch. (Please see download of map)

The works will be completed two hours either side of high water and are expected to commence on the 1st August 2018, weather permitting.

All work will be shore-based and there will not be any vessel operating on the river.  However, Mariners are requested to take due care and consideration whilst passing these works and keep their wash to a minimum.

Thank you for your co-operation.

Captain Susan Harrison MNM
Harbour Master
25th July 2018