Havengore Bridge Update (08.01.19)

 Unfortunately, Havengore Bridge remains closed to marine traffic. The specialist contractor has removed the leaking hydraulic manifold for refurbishment and will return to re-fit it on 23 and 24 of January. Following this, and subject to satisfactory testing, the bridge will be returned to service.

Thanking you for your continuing patience.

 

Nicki Uden – Community Liaison Officer, SHOEBURYNESS RANGE
Careline: 0800 0560108
Email: nuden@QinetiQ.com

 
 
 
 
This information is given by the CHA in good faith and updated when notified by MOD, however the situation may well change on occasions and we therefore advise before making any trips to contact the MOD direct to check the status of the Bridge.