Potton Bridge Survey Work

QinetiQ are intending to carry out inspection work to Potton Bridge on 4th and 5th October 2017 between 08:00hrs and 18:00hrs. The work will involve a temporary platform being lowered beneath the bridge.

All vessels will be unable to use this route and navigate through the bridge on both days. Road vehicles will also not be permitted to cross the bridge.

CH2M who are carrying out the inspection have stated they will retract the platform between 12:00hrs and 13:00hrs on both days to allow vehicles to cross and vessels to pass through the bridge.

For further information please contact:

Mr Edwin Birch, Project Manager
D 01702 383620
ejbirch@QinetiQ.com
 

Captain Susan Harrison MNM
Harbour Master